The team installed two grandstands with a total of 3,500 seats along the finish line and additional platform spaces for VIP lounges entirely by hand. Walkways, several platforms for the catering company, and sanitation facilities were integrated into the substructures of the grandstands. To accommodate the media and provide the necessary event technology, NUSSLI set up several podiums and camera towers along the slopes and assembled substructures for video walls. Most of the camera towers were flown to their respective assembly sites by helicopter.
The first material deliveries for the camera towers and platforms arrived as early as last November to be assembled on a golf course. The use of forklifts or cranes was forbidden on the course, which meant that the 220 tons of material had to be transported from a distant parking lot to the actual construction site using slope maintenance machinery.